Connecting Hybrid Renewable Generation to the Grid
Bringing 75 MW of wind and solar generation into a common grid connection required a dedicated 220/30 kV substation solution. Izharia, now operating as Quadrante Global, developed the detailed construction engineering for Merengue II. Designed as a 220 kV outdoor facility with 30 kV indoor switchgear and a single-busbar configuration, the substation comprises one line bay and two 220/30 kV transformer bays. The engineering scope covered earthworks, civil works and steel structures, electromechanical assembly, protection, control and metering systems, and auxiliary services.