Harnessing Wind Power in Castilla-La Mancha
Nine Nordex N163/5.X turbines form the core of the 50 MW wind farm, supported by the civil and electrical infrastructure required for their operation. Izharia, now operating as Quadrante Global , developed the construction project engineering, covering eight 5.55 MW turbines and one 5.60 MW turbine. The engineering scope included internal and external roads, turbine platforms, a measurement tower, drainage systems, the medium-voltage network and storage areas, together with a review of the turbine foundation design.
Market
Sector
Energy
Services
Location
Castillejo de Iniesta, Cuenca, Spain
Status
Completed
Client
Leyco S.A.