Boosting the Wind to drive the Energy Transition


Terras Altas de Fafe, Nave, Mourisca and Serra do Ralo Wind Farms

The project included boosting the power of 4 existing wind farms – Terras Altas de Fafe, Nave, Mourisca and Serra do Ralo – with new-generation wind turbines totalling 4.5 MW, +100 m high and 150 m in rotor diameter.

Access, platforms, cable trenches and power lines were built to ensure the assembly and connection of 11 wind turbines, equivalent to the installation of 49.5 MW of 100% renewable energy, thereby reducing dependence on fossil fuels and cutting greenhouse gas emissions.

Key numbers

Location

Portugal

Year

2022-2023

Status

Concluded

Client

TrustEnergy

Total power

45 MW

Cable trenches

12 km

Airline

2,4 km

Impact

Quadrante’s Intervention in this project was multidisciplinary, specifically in the areas of Owner’s Engineering, Construction Management, Risk Management, Civil and Electromechanical Construction Supervision, Safety, Quality, Environment and Archaeology.